Hampden sewer project to begin
About 9,000 feet of line will be replaced this summer and fall
By Eric Russell
BDN Staff

HAMPDEN, Maine — The town is set to begin a $1.85 million sewer replacement project on Monday and the work is expected to last through the summer and fall.

Town Manager Sue Lessard said the project, which was approved by a voter referendum last November, will replace 9,000 linear feet of old sewer line in a part of Hampden.

The streets that will be affected are: Route 1A from Riverview Road to Frances Drive and from Wheelden Heights to Hillside Drive, Patterson Street, Wheelden Heights, Northern Avenue, Perry Road, Coolidge Avenue, Coolidge Avenue Extension and a portion of Old County Road.

Sargent Corp., which has offices in Hampden, was the low bidder for the project and was awarded the contract, Lessard said. The company has done significant work for the town in the past, including a similar sewer replacement project in 2006.

“The contractor is responsible for ensuring that traffic can move at all times,” the town manager said. “Our goal is to minimize the impact to homeowners during this process. … We have a good team in place to see this project through.”

The project will be paid for by a bond, but Lessard said user fees are expected to increase as well. The town has not increased sewer rates since 1998.

“We understand it’s not the perfect time for any increase, but we have no choice,” she said. “There have been a number of breaks and problems in lines recently. Once that happens, we have responsibility to users.”

In 2006, the town completed a sewer replacement project along Route 1A between the Souadabscook Stream and the Crestwood Trailer Park. That project was bonded at $1.5 million but was largely paid for by user fees already in reserve.

As proposed, the rates would increase from $3.28 per 100 cubic feet to $4.28 per cubic feet. For an average customer, that means an extra $24 per three-month period, Lessard said, which would still keep Hampden in line with other area communities.

The sewer reconstruction project is expected to be completed by early November.

erussell@bangordailynews.net

990-8167

Not registered? Click here
E-mail this
Print this
Comments
3 comments on this item

You need a good sewer.

Oh boy here we go again! does anyone remember back in 2004 when they redid the lower part of 1A? traffic tie ups, dirt roads, even that poor lady who had the sewer back up into her brand new house! honestly, im glad i live in brewer now

I'm glad I use an Outhouse !

You must be logged in to post a comment. click here to log in.
Local News
AUGUSTA, Maine — Several groups advocating for open government are joining a bipartisan group of lawmakers to propose …

BANGOR, Maine — The U.S. Postal Service, which is under a time crunch to move out of its current location, will have …

ORONO, Maine — University of Maine President Robert Kennedy today will announce he is stepping down from the position …

GUILFORD, Maine — Residents took time during the annual town meeting Monday to recognize a civic-minded local …

Secretary of State Matthew Dunlap’s job is to run elections, oversee the state archives, ensure compliance with …

Recent comments
On 3/17/10 at 5:50 PM, JoeDoe wrote: " do as the chinese do " ~ Come ONnnnn Joe ~ Make Up Your …

On 3/17/10 at 5:58 PM, TooBadSoSad wrote: Repeated separate thumbs down will cause comment to be hidden Keep it up, …

It Really IS As Simple As Goin Fishing In A Can of Sardines Keep Showing Da Audience I`m Sure All R …

Keep it up, and I will spill my beans. I am sure you don't want that.

On 3/17/10 at 5:41 PM, TooBadSoSad wrote: Repeated separate thumbs down will cause comment to be hidden He was …

Copyright ©2009 Bangor Publishing Co. All rights reserved.

Powered by: Creative Circle Advertising Solutions, Inc.